I set up the following scenario.
- I have a release that occurs at the end of every two sprints.
- I configured my team to be able to handle 13 points per sprint.
- I created an epic equal to 13 points with 3 stories adding up to 13 and 1 story equal to 8 points.
When Portfolio schedules the work. It set's it up for 2 releases. It adds 3 stories to the first sprint but is ignoring the 2nd sprint. The 4th story shows up in the first sprint of the 2nd release.
I want the 4th story to show up in the 2nd sprint of the first release. Is there any special configuration I need to do?