I'm a complete newbie to Agile and JIRA and I'm learning as I go so please bare with me!
Let's say I have 3 resources and each are working on 3 different tasks that take one day each.
In a Gantt chart, the total time until completion would be 1 day. All your resources are allocated in separate tasks, therefore, in one day all 3 items are complete.
In Jira Agile, I'm using time estimation, not story points. When I drop in these same 3 tasks allocated across 3 assignees in one sprint, sprint estimate is 3 days. Is there an agile fundamental I'm missing here? Why would it not be 1 day?
Any answers, advice, or pointing in the right direction would be most appreciated. Thanks!
- Len