This question is in reference to Atlassian Documentation: Invalid date when trying to Log Work on Issue in JIRA
I am trying to filter for tasks where "Log Work" "Date Started" is within current week. But the "Date Started" field isn't showing up in my JQL. Any idea why?
Have you tried using worklogDate e.g.
worklogDate >= startOfWeek() && worklogDate <= endOfWeek()
Thanks Robert, not able to see that field either, screenshot attached.worklogDate_NotAvailable.PNG
Vikrant, could you confirm which version of JIRA you are using?
https://jira.atlassian.com/browse/JRA-40973
Hi Robert, here it is: Atlassian JIRA Project Management Software (v6.3.12#6343-sha1:0d8f4aa)