How can I get a burndown by project using story points? We do not have assigned versions, we are only two sprints in, but I would like to see a project burndown.
Ryan - Don't think you've provided enough detail to get a qualified answer. What version of Greenhopper are you using? If you are using an older version "fix version" is what it's going to be based on. The newer releases have sprint reporting more fully integrated
Sure thing David,
Version is 5.10.5.
Looking for a burndown for the entire product, not one based on versions. We have not assigned verisons as we have not decided on a release point yet.
We are ending our 4th sprint tomorrow, and I would like a project level burn down of all the work done vs all the work in the PBL. So, not a release burn down, but a project burn down.
If you are using the classic greenhopper (plan/task/chart are separate menu options), then you need to setup a heirarchy of versions. Each version is a sprint with the root version being your ship version with a targetted ship date. The charts will project to the ship date if you choose that root version.
> Construction (start/end dates)
> > Sprint 1 (start/end dates)
> > Sprint 2 (start/end dates)
> > Sprint 3 (start/end dates)
If you set that up, the charts work well. If you do not put in the dates, the charts do strange things. The heirarchy can be setup at any time inside the cards on the right side. The default is "parent: none".
You also get a velocity bar graph showing each sprints story point velocity over time.
The key is to use versions for sprint tracking.
Darren,
Thanks for the input. From an Agile standpoint, that is crazy as that is NOT Agile, even a little.
That said, I understand how you are setting up the work around. Too bad Greenhopper can't do this using the actual Sprints. Perhaps in the future!?
Rally and Collabnet both support this very basic Agile chart.
Thank you again.
Ryan - The new Scrum boards released 'officially' on 5.10 do exactly that. They get away from having to use versions as sprints. If you are still using task and planning boards you should look to migrate away from them to get what you need with the tool
https://confluence.atlassian.com/display/GH/GreenHopper+5.10+Release+Notes
Ok I totally agree and we are not using versions as sprints in the new versions. Hence missing the Project Burndown ability. Like I told Darren, it would be great if Greenhopper could do that using the actual sprints instead of the versioned method.
We need this as well (a whole project burndown chart), using the new version of Greenhopper (V6.01). It's very confusing for our users currently, they can select "Greenhopper Burndown Chart" from the dashboard gadgets but it doesn't function correctly.
I tried poking atlassian on this, a long time ago, but nothing came back. I just dont understand how we dont have a simple SCRUM dictated project burn down.
In an ideal world, what we want is the following:
- A way to display a story-point burndown for an entire release in a Rapid board chart (Fix Version is probably still a good metric for this, as long as we can set the start/end dates for the chart somehow).
- Burndown by Issues chart in Rapid board
- The ability to display any/all Rapid board charts in a Dashboard.
I'm a fairly new GH user and this is killing us as well.
+ 1 from our company
+1 ... many valid points are raised here.
In case you need a short-timeframe solution and can't wait until all these get implemented in Greenhopper (ah, sorry, JIRA Agile), consider coding them with the JIRA PDF View Plugin. It is shipped with a simplistic "burn down chart" template to use as starting point.
You can merge any arbitrary set of issues with that template, so you can get the burn down on any granularity: per project, per version, per sprint, per anything that can be coded as a JIRA filter.
Also, you can compute the burn down in mere issue count (this is how the factory default template works) or in story points (requires some scripting).
Burn Down sample PDF
https://jira.atlassian.com/browse/GHS-9063
This was requested here. And since Atlassian won't let me change email addresses, and I changed jobs, I dont have access to this question any longer.