When adding a new issue I can select the sprint to add it too. We are currently working sprint 3, and have a couple of future sprints planning up. However sprint 1 is still hanging around as acitive.
None of the Agile boards show sprint 1 just sprint 3... how can i find Sprint 1 and close it?
2015-02-13 14_12_14-Create Issue - JIRA.png
Search for issues with that sprint in the issue navigator and see if there are any issues in that Sprint. If you find one, create a board that will include the issue and then close the sprint from that board
It seems that the sprint has no issues in it, and on the board it says "no active sprint"
JQL (sprint = 3) Maybe if I create a blank issue in the sprint it will appear and let me close it....
That worked Crazy system!