Hi Team,
I'm capturing agile metric for my project.
So wanted to check for the velocity.
Though there is velocity chart available, but it shows up only for last 5 iterations.
Hence had to go for manual calculation.
Manual calculation logic and chart output is giving different data.
explanation is as follows:
My understanding is,
Commitment Story points = All story points in an iteration that was planned to be completed (which may have been removed or incomplete at the end)
Completed Story Points = All story points that has been completed at the end of an iteration
My query is on commitment story points for Velocity chart that is as follows
- I click on a sprint report that gives me details of Completed Issues, Issues Not Completed, Issues Removed From Sprint
- So to calculate commitment story points, I simply add up story points for Completed Issues, Issues Not Completed, Issues Removed From Sprint
- For Completed i use Completed Issues
- For commitment story points, manual calculation is giving me wrong data whereas the velocity chart is showing different data
For example
Velocity for iteration/Sprint 48 is
Commitment = 74
Completed = 34
but with manual calculation
Completed Issues(32) + Issues Removed From Sprint(10) +Issues Not Completed(67) =109
so as per graph/chart its 74 whereas by manual calculation its 109
Report and data is given below for reference
image2015-7-30 12:13:12.png
Click on customer-sprint 48
View Customer - Sprint 48 in Issue Navigator
Closed Sprint, ended by KING, David27/May/15 9:47 AM - 10/Jun/15 10:00 AM Linked pages
- View in Issue Navigator
Completed Issues
View in Issue Navigator
- 1. Issues Not Completed
- Issues Removed From Sprint
- View in Issue Navigator
*Summary details removed intentionally