We have setup our project however the Chart Board for our Sprint 1 is not updating correctly.
We had 15 Total Issues and we marked them off as closed, however we only closed 9 of them a day after the sprint ended (because that is when the review is). Now we are left with a chart that shows a Remaining Values line with 9 left when we actually completed all tasks.
The Sprint stats on the right handside shows 15 resolved however it appears that date of closure is affecting the chart.
Is there anyway that I can fix this?