What is the difference between task hours and original estimate when used by Greenhopper?
Looks like the estimate is based on task hours and not Original Estimate field.
Is there a doc on the calculations??
Also we are looking at how these fields are affected by the guidline field. It does not show a straight slope line From the DOC: Guideline (solid line) — The ideal burndown. This is computed with the remaining estimates, not the original estimates of the hours remaining at the version's start date. Hence, this calculation makes the guideline slope more accurate and precise.