HI All
We are stuck in a time tracking issue on jira.
We usually estimate our stories in days and later on the stories are broken down in tens of sub-tasks. Each developers again estimates each of the sub-tasks and logs time on sub-tasks
What it effectively means is that the total estimate gets over-inflated because we are counting the estimate twice (once on parent story and then again on sub-tasks).
Things get even more complicated when you run agile, and due to this the burndown get over-inflated.
What is the possible solution to our problem of double counting of estimates?
Rahul