We are using the time tracking for our scrum board. The task has an estimated hours of completion during planning and the person who picks up the task will burn down the hours using remaining time field. How do you show when the person estimated a task for 2 hours and comes to the stand-up and says he/she burned 2 hours yesterday, but has 2 hours remaining today in order to complete the task?
If they updated the tasks it would show 2 which would be flat in the reports.