Hi Community đź‘‹
Plans change. A piece of work takes longer than expected, a milestone moves, or your team gets ahead of schedule. Updating the work that depends on it shouldn’t mean adjusting every date individually.
We’re introducing Dependency Rescheduling in Jira Plans, making it easier to move connected work together directly from your timeline. 🙌
One change, connected updates
Hold Shift while dragging a work item’s timeline bar to reschedule its dependent work alongside it.
Moving the work item three days later shifts affected dependent work three days later too, preserving their durations and the spacing you’ve already planned. You can also hold Shift while extending or shortening a work item’s due date to shift dependent work by the same number of days.
For long dependency chains spanning multiple teams, this means fewer individual date adjustments as your schedule changes.
Hold Shift while dragging a work item to move dependent work together.
A launch slips, but you don’t have to rebuild the schedule
Imagine you’re coordinating a product launch. Development blocks testing, and testing blocks the launch.
Development needs another three days. Instead of moving development, then testing, then launch individually, hold Shift while extending the development task’s due date.
Plans proposes shifting the downstream work by three days, keeping the time you’ve allowed for testing and the gaps between those activities intact.
Review the proposed changes, then apply them together. Less manual date maintenance, with you still in control.
See what’s changing before you apply it
When your adjustment affects other work items, a confirmation dialog lets you review the proposed date changes.
You can choose to:
- Apply all changes to move the affected work together.
- Change only this work item to keep your adjustment without rescheduling the work that depends on it.
- Cancel to discard the proposed changes from this interaction.
Applying changes updates your plan, but doesn’t save the new dates to work items in Jira. Review them in Unsaved changes, then save them to Jira when you’re ready.
Confirmation dialog showing affected work items and their proposed dates.
Try it in your plan
- Open your plan’s timeline and find a scheduled work item with work that depends on it.
- Hold Shift, then drag its date bar or due date resize handle to the intended date.
- Release the mouse and review the proposed changes.
- Apply the changes, then review and save them to Jira when you’re ready.
📦️ Rolling out soon
We’ll be gradually rolling out dependency rescheduling for all customers using Jira Plans. If you don’t see it immediately, look out for it as the rollout reaches your site.
Tell us what you think
What kinds of schedule changes would you use dependency rescheduling for? Tell us in the comments. đź’¬