Upgrading from 6.4 to 7.x in JIRA. Do I need to be aware of any upgrade issues beforehand and what they are?
Does someone have a list or items which can cause upgrade to fail?
From 6.4 to 7.1 is pretty straight forward, just the usual stuff:
Save a copy of your:
server.xml (http/https ports)
cacerts (ssl certs)
web.xml (depending on your customizations)
Do the add-on compatibility check, and disable all plugins not supported by the target version.
Once JIRA is upgraded, update UPM first, then upgrade all plugins.
And as usual, ALWAYS do it on a test-instance which is a 1 to 1 mirror of your production, before going ahead and doing it something production critical.
Upgrade JIRA Agile to the latest version before moving to 7.0
What are the challenges that arise if I don't upgrade JIRA Agile to the latest version before moving to JIRA 7?
hi jonas ,
have you tried upgrade from 6.4.4 to 7.0 ? do u have a list step by step for safe upgrade?
because i have plan to upgrade from 6.4.4 to 7.0 in the same machine/server
thx,
Lukman