Hello,
Somehow every new sprint, we have existing CLOSED tickets that get transferred to the new Sprint.
It is happening, when someone is closing old Sprint and opening new Sprint.
Thanks,
Denys.
Have a look at one of these "closed" issues. Were they in the far right hand column of the board when the sprint was closed (look at the status at the time of closing and the board column mapping). Also, did they have one or more sub-tasks? If they do have sub-tasks, check the same for the sub-tasks - were they in the far-right hand column too?
Statuses "Closed" and "Resolved" are Unmapped in Board. Column "Done" contain tickets only with status "Ready for Release". Tickets had been closed before Sprint has been closed. Such tickets have sub-tasks and/or linked issues which are not "Closed" but "Ready for Release"/"Opened". Also i have found tasks which are in progress and moved to new sprint, those tasks contain sub-tasks in "Opened" and "Ready for Release" states, all those sub-tasks also automatically moved to new Sprint.
Right, that makes sense.
For an issue to be seen as closed by a sprint, it has to be in the right-hand column of a board.
Your closed and resolved issues, and the ones that have sub-tasks that are not done, are moved to the new sprint because you've told JIRA they are not done.
I actually have the exact same problem, BUT my board has the a done column with all the closed and resolved tickets mapped correctly. Basically the sprint closed, a new sprint was started and over 200 tickets that were closed from months ago (several sprints past) somehow were added to the new sprint automatically. I checked the history in the individual tickets and none of them have an action listed that put them in the new sprint. And the board filter hasn't changed and there's nothing in the audit log to explain how it happened. Very concerning that we have to manually update each individual ticket since bulk update doesn't allow us to remove one value from a series of sprint values per ticket
My team is experiencing this issue too and it's beginning to cause problems. A solution to this would be great. We can't even see these random other tickets that are going to be added before we start the sprint, because they're not even listed in the filter of the board we're creating the sprint from (because the random tickets are from another project).
Jira only has two ways to add issues to a sprint:
1. A human adds them
2. You close the previous sprint with issues not in the most right hand column
One of those two has happened. 2 often confuses people if they reconfigure columns though.
Hi Nic,
Unfortunately, you're wrong, it's not that simple.
There are tickets which have been closed / done / resolved from other projects being added to newly created sprints.
I've checked other solutions which have suggested the mapping of statuses and it all looks to be correct.
The other problems is that somehow we're getting crossover, i.e. tickets from project B are somehow ending up in a new sprint of project A. How can we groom our backlog and plan upcoming sprints if they are continually getting messed up?
Cheers,
Rebecca
Hi, I do not want to have Closed / Done and Resolved tickets in the same column because it is different - is there not a way for having all three different statuses in one column and still dont make them to be transfered to the next sprint? @Nic Brough -Adaptavist- @Rebecca Zeus @Marisa Hager
No, the done column is the definition of done. If you want something to transfer to the next sprint, it must be in another column.
I am looking at the same issue right now.
- A bunch of closed tickets that have not been modified in a long time were added to a newly created sprint.
- Modification date has not changed (old tickets still show 2018 as updated/resolved).
- Issue Activity does not show any recent change in values for Sprint field.
- Old issues turn up in the right most column based on their status.
- No subtasks in many of these old issues.
We're experiencing the exact same issue
Hi,We are phasing exactly this problem. Out of the blue very old tickets (about 60) show up in the just started sprint in the done column. The shown tickets are about two years old. Opening such an old ticket does not show any modification in the history for the last years. I see for example ticket-64 while creating a new one today will be ticket-2978 If I look at the 'Sprint' value of ticket-64 it shows the name of the current sprint what is: "Sprint 86 wk46_47" The string "Sprint 86 wk46_47" did not exist at the time ticket-64 was actual and now it is suddenly filled in. So, to me this looks like Jira is applying changes to its internal database by mistake. A bug. It seems to happen at sprint closure. The updated tickets are not related to the closed sprint or the backlog. The modification are done without a trace, at least not on user level since history is not changed at all.
I really hope this ticket, defect report, is taken seriously
Thanks, Geert-Jan
This is happening to me every time I'm starting new sprint. @Bloomberg Industry Group please fix this issue. We don't want any random closed tickets to be added to the newly started sprint. After all the sprint planning and ensuring we've reviewed every single ticket so the report will be organised. But this issue is really undermines that. Please fix this asap. Thanks!
There is nothing for Atlassian to fix here. You might need to fix your board configuration though.
The issues being added to the new sprint are added when you close the last sprint with issues that are not "done" (they and all their sub-tasks are in the last column of the board)
yes, we have the same issue, and yes, there is a bug needs to be fixed, configuration of board is ok, the issues are seen to be closed in old sprint reports. and nobody moved them there manually, also history sais none did it! so pleas stop saying there is no issue when there obviously is.
Still facing the same issue, any resolution found so far?
Not sure if this helps everyone. We have our JIRA instance connected to our JIRA Align instance. And what we found is if a Feature in JIRA Align is moved from one Program Increment (PI) to another, it is moving the accepted stories under that feature to a sprint a couple of weeks out. So the ticket was updated on 4/28 and it moved it to our already created sprint of 5/17-5/23. So this is definitely NOT an issue with our board setup. We have a ticket in with Atlassian on it.
Hello Richard,
Did you get any update from Atlassian?
In my team also I am facing same issue.
Its not a manual error for sure.
I don't think this is quite the same problem as the rest of the conversation was about. I suspect the board setup here is correct, and it's Align (rather than a human) moving things to the wrong place.
I'm facing the same issue. Tickets are marked as Done Done Column is on the most right No recent activity was done on the ticket before starting the sprint I've also verified my board filters No sub tasks / linked tasks are in open status and they're also in the most right column
Still I'm seeing a few closed tickets in my new open sprint. Technically it should not be the case and I'm out of options atm. Any help will be appreciated.
You need to re-check the configuration. Can you pick an issue that has gone wrong and show us
Also can you confirm this is happening when you close the initial sprint?
It looks like you're new here. Sign in or register to get started.