Hello,
We are preparing to migrate from Jira Data Center to Jira Government Cloud and are looking for timeline estimates from others who have completed migrations of a similar size.
Environment details:
Jira Data Center Version 9.12.31 (Soon to be on 10.3.19)
1-node Jira Data Center deployment
~400 projects
~410,000 issues
~1,300 users
~700 custom fields
12 installed apps total; 4 apps will be migrated (Email This Issue, BigPicture, Jira Workflow Toolbox, EazyBI)
Identity and access:
SCIM provisioning will be used
SSO is already fully configured
Environments:
3 Jira environments (1 production, 2 non-production)
Both non-production environments contain non-production data
Additional context:
Only 4 apps will migrate; the remaining apps will not be brought to Cloud.
---> We are seeking general expectations on how long migrations of this scale have taken (for example: 3 months, 6 months, 9 months, etc.)
We would appreciate any examples, guidance, or ranges based on past migrations of a comparable size, including time needed for planning, test runs, validation, and final cutover.
Thank you