Hi, may I know how can I configure different estimation units for Story and Sub-Task please? ie. I want to enter estimates for Stories in Story Points, and Days in Sub-Tasks.
Please advise.
Estimation units are done by board, not issue type. It doesn't make any sense to do them separately by type - "my story is 4 story points, but I've got a task which will take 2 days" renders them incomparable.