Hi
We use jira-agile and we are facing a problem with burndowns getting overinflated.
Scenario: We have a user story which is estimated at start of sprint say 10 days; the burndown displays 10 days of work. But during the course of the sprint, developers break down the user story into smaller sub-tasks and assign estimates to it. Now these sub-tasks are basically fragments of the user-story rather than additional work, however, the burndown gets inflated due to these addtional sub-task estimates.
What is the way out of this problem?
Rahul