What is the criteria for Release 'Off Track or On Track' is it automatic set?
Hi @SianS
Release status is calculated based on the target dates of any issues assigned to the release. Here are the definitions:
On-track - If the all issues assigned to the release are starting and finishing before the release date then the release is on-track. Also if there are no issues assigned to the release or none of the issues assigned to the release has dates then also it will be on-track.
Off-track - If any of the issues is starting or ending beyond the release date then the release is off-track.