Hi,
I have following automation to update Target Date when Estimates (d) is updated:

- Target Date = customfield_17972
- Start Date = customfiled_17971
- workdaysToAdd = variable to store Estimates (d) in day
workdaysToAdd = {{#=}}{{issue.timetracking.remainingEstimateSeconds}}/28800{{/}}
Syntax for Edit Action as follow:
{
"fields": {
"customfield_17972": "{{#issue.customfield_17971.toDate}}func=plusBusinessDays({{workdaysToAdd}}){{/}}"
}
}
I want to run above rules in real time in Advance Roadmap. With normal condition the rule will apply after I Review and Confirm change on the field.

Is there any way to make it run before Review and Confirm? I want to see the updated Target Date in real time after updating the Estimates (d)
I am running under this JIRA version; Atlassian Jira Project Management Software (v9.12.17)