Quick question:
We have a board which has 2 projects link into it. BUT even thought the used have permission to start and stop sprint only one Sprint can be started? Any idea how to fix?
Hey @SianSOnly one active sprint is allowed per board by default in Jira. To start multiple sprints, you need to enable the Parallel Sprints feature in Jira settings (requires admin access). Also, ensure sprints are created on project-specific boards and users have the correct sprint permissions in all linked projects. Let me know if you need help with the setup!
Hi @SianS
Maybe the parallel sprints feature will be helpful? This feature allows you to run multiple sprints at the same time
You can turn it on under Settings > Products > Parallel sprints
More about it: https://support.atlassian.com/jira-software-cloud/docs/use-parallel-sprints/
Kind Regards,Weronika
Thanks so much it works