Hi everyone,
Some teams in my company have always used time-based estimation in Jira, using the Original Estimate field and the native Time Spent field to track progress and compare estimated vs actual time.
Recently, we have integrated Jira to our ERP system. Now, logging time in Jira requires selecting a valid Internal Order from the ERP. Since not all teams are part of this process yet, they can’t use the Time Spent field anymore.
However, these teams still would like to use Jira to:
- Estimate in time (not story points, not issue count)
- Track the actual time spent
- Compare estimates with real effort
I know we can use custom fields for estimation, but I couldn’t find a good alternative to track actual time spent without using the native Time Spent field.
Using a generic Number custom field feels too limited and doesn’t provide the same flexibility or reporting capabilities.
Has anyone faced a similar situation? How did you deal with it? Any workarounds or suggestions?
Thanks in advance to anyone who can share their experience or ideas!