How do you handle bugs during the sprint planning meetings? All of the stories in the backlog are given story points. The team has capacity of X story points per sprint. So I know how many stories I can fit into a sprint but how do I add bugs into this mix since a bug does not have a story point estimate on it?
Thanks,
Mike