How to change status of Parent task(from on hold to in progress) when child/ren (clone sub-task in other different project is closed/resolved)- Automation rule
@Wojciech Szczygłowski
Can you share screenshot of the automation that you have written so far?
if you have not written anything so far, I suggest you take a first stab at it.
but it's not working i mean -no action were performed in log🤔
Could you show the audit log entry of your last run of this script?
Kind regards,
Dick
I wrote this quick automation to test. It is working fine at my end
Do note that as far as i Understand you can't have a subtask in one project and parent task in another project.
Epic can be in another project while StandardIssueType can be in another project