This question is in reference to Atlassian Documentation: Settings estimates with story points
Lets say Winston is a member of two teams. First, the Sharks with Greg. The Second, the Tigers with Anatoly. Both the Sharks and Tigers are set to a velocity of 100 points.
If i create an epic/stories under Initiative A and assign them to Winston... how fast will he work on them according to the schedule? Presumably at 50 points velocity.
Will my stories in Initiative B, which is assigned to the Tigers (Winston and Anatoly), will they be scheduled after he's finished with Initiative A? I'd imagine Portfolio would have Initiative B working at 50 points velocity, because it knows Winston is working on A instead. Despite Winston being a part of both teams. ?
Apologies if my question isn't clear.