Two sprints are flipped in backlog on 2 boards in jira Data center
Hello @khushboo_puri
Can you provide more of an explanation of what you mean by "flipped"?
A screen image showing what you are seeing, and an explanation of how it is not what you expect would also be helpful.
Good day. This could be shared sprint as well. Following link should help. https://community.atlassian.com/t5/Jira-articles/Knowing-when-you-have-a-Shared-Sprint/ba-p/944613
When someone refers to something as being "flipped," they usually mean that the image or content is displayed in an unexpected orientation, like being mirrored or rotated in the opposite direction.
Sprint 3.4 is displayed then sprint 3.6 and then sprint 3.5
We need 3.4, 3.5 , 3.6
Active sprints will display above Planned sprints in the Backlog.
You can reorder Planned sprints. Refer to:
https://support.atlassian.com/jira-software-cloud/docs/reorder-a-sprint-in-a-company-managed-project/
It is not possible to change the order of Active sprints. There is a change request about that:
https://jira.atlassian.com/browse/JSWCLOUD-17512
I have not found documentation that states how Active sprints are ordered.
Great answer. I appreciated.