Hi Experts,
I am new to JIRA Automation and looking for a way to sum-up Story points that are at the child issues level to the Epic level. In my case, the child issues can be from different jira projects
Example:
EPIC is in JIRAPRJ1 project and has following linked issues:
STORY in JIRAPRJ1 project
TASK in JIRAPRJ2 project
TASK in JIRAPRJ3 project
Now, I want that if anyone adds/removes story points in Child issues in
JIRAPRJ1,JIRAPRJ2, or JIRAPRJ3
then, the corresponding value reflects on EPIC.
I see there is already an automation template available. It does work very well for the issues in the same project but doesn't update when the child issue sits somewhere else.
Any guidance on how this can be done.
Thanks in advance,
Rahul