I am working within a Timeline view and dealing with several Tasks, under an Epic, all under an Initiative. In the course of a project, some Tasks get delayed, and I'd like dependent Tasks to automatically shift to the right reflecting the delay. I can't seem to make this happen automatically, so with an Epic containing several Tasks, this manual process is very tedious.
How do I make the Timeline view act more like a traditional Gantt Chart where dependent tasks are automatically shifted to the right or left depending on their predecessors completion or delay?