Hi there,
we are currently trying out JIRA + Tempo to see if it meets our planning needs. Is there an automatic solution for the following problem?
- User was assigned an issue which spans over a couple days, each with about 60% capacity
- User now has an extra issue planned for a full day (e.g. an external workshop). The first issue that was automatically distributed over all the days does not adapt its capacity for the day though
- This leaves the person with a single day of 160% and all other days at 60%. I don't want to plan individual days for all issues, but sometimes it is necessary - and these should "make themselves room" so the person is not overbooked - especially when left and right of the day is enough capacity.
If there is no automatic solution, can I trigger something like a "redistribute planned time"?
Thanks!