We have Structure set up so that if we drag and drop an issue start or end date on the Gantt chart then it updates the Target Start and Target End date for the issue.
What we have found though is if we add/update a dependency within Jira Structure then the issue timeframe changes on the Gantt chart within Structure but does not update the Target Start and Target End Date on the issue in Jira.
Is there a way we can configure Structure to update these dates in a similar way to how it does it when moving it within Structure?