Hello all,
A bit of context for my query:
I have two main rules currently which trigger eachother. One detects when a subtask (Lets call it subtask A) start date is changed and edits the corresponding due date based on a custom variable called 'Sub-task Length in Days)

I also have another rule that detects when a sub-task due date is changed, and changes the start date of the following corresponding linked subtask (Subtask
to match this due date, such that they would appear synchronous on a Gantt chart.

However, as I have a significant amount of subtasks in this order (Subtask A-Subtask X), my largest issue is that the loop breaks after 10 iterations. Is there a way my automations could be rewritten to avoid this issue? Is there any way to complete this without automation?
Any help would be appreciated!