HI All
We are trialling the portfolio for jIRA plugin. What we observed is that the portfolio plan is not linked in any way to the underlying JIRA data. in other words, i cannot build my portfolio plan based on my actual data on jira.
e.g.
- an assignee on JIRA issue is not sync'ed to the Members on the issue on Portfolio plan.
- The agile sprints on the underlying jira-agile does not show up on the portfolio plan
- An issue in Sprint 2 say on jira-agile does not set the same issue in sprint 2 on portfolio plan.
Is portfolio just a forecasting tool or can i customise it to use it as project management tool too?
My version of portfolio is 1.12.4 hosted on JIRA 7.1
Rahul