Hey,
I need to report the total progress (%) of my project at the Capability level in connection with each month (and release) reporting.
Is there a way I could report :
- what the total completion rate (%) is today and
- what it is at the end of the release (end of the month)
I'm presenting the current completion rate (%) using the Structure plug-ins progress data (based on time tracking fields: original estimate - remaining estimate). Do I have to create a custom field where I store the current completion rate to be able to compare it to the completion % at a certain point in time, or could the information be presented using, for example, time series?
I have rich Filters and structure plug-in in use, but no analytics tools. Thank you already in advance!