Hi All,
My automation Rule is not working for below mentioned scenario. Can you please help. Thanks
Whenever I create a bug:
3 subtasks should automatically create within that bug.
Welcome to the community @Uzmii !
Hi Uzmii, this is my suggestion for this rule
@Bao Truong thank alot for your timely response. I have tried your method. It creates only first subtask and does not create the 2nd and 3rd subtasks.
@Nikola Perisicthank alot for your timely response. I have tried your method. It creates only first subtask and does not create the 2nd and 3rd subtasks.
@Uzmii Can you post a screenshot of your automation rule?
@Nikola Perisic Your method works but I have got the issue. All 3 subtasks are getting created but only when I refresh the page after creating the bug. Any reason why is that happening?? thanks
So I create a bug.
Only first subtasks is visible.
When I refresh the bug. Rest of the two subtasks start appearing.
@Uzmii I believe the reason why only one sub-task is showing up on the UI is that the rule takes some time to run. When the bug was created, only the first sub-task had been created, hence only one sub-task is being displayed on the UI.
To view all the sub-tasks, you need to refresh the page. However, there is no need to worry as all the sub-tasks have been created properly and all the data has been stored correctly.
Hi Bao.. Thanks alot for your help. It worked.