Hello,
I need to create an automation rule to reflect the correct total of the "Time tracking" field on Epic as a sum of the "Time tracking" values of its tasks.
I made the following configuration (the screenshots below), but it doesn't calculate the total value correctly. When I log 5 min to a task for the first time after rule activation, it returns the correct total value for epic: 4d 1h 25m. But when I log 5 min for the second time, the "Time tracking" epic field shows me an enormous value: 1w 3d 3h 5m instead of 4d 1h 30m.
I'm not sure if it's important or not: some of my tasks already had time logged on before rule activation. So I need the epic total to reflect these values as well + newly logged values.
Thanks.

The advanced "Edit issue fields" block is the following: