Is it possible to add the Team's Holidays in the Project Calendar and Timeline so that it shows a clear representation of when Issues can be worked on ?
Thanks
Hi Olivia,It's Mary from Planyway
I believe the only way to do it is to create issues for the holiday and then get them visualized. If you're afraid of getting too cluttered, I recommend creating a Holiday board, that's how we manage it in our team. We have a separate board called holidays where we create issues that mean somebody's holiday. Then, with Planyway addon we create a timeline/calendar view with multiple boards connected. So, you can connect your project boards and holiday board and view it all together. It's quite simple and straightforward.
Thank you Mary will look into your suggestion, looks like a good set up