Hello,
We have a development team who is looking for us to configure workflows like so:
SUBTASKS
To Do-> In Prog-> Done
STORY
Open-> In Refinement-> To Do > In Prog -> Ready for test -> In Test -> Post testing> Done-> Closed
Stories cannot be manually transitioned through statuses, the transitions of subtasks will trigger this.
Subtasks currently = (Dev subtask, QA subtask, Performance Test subtask...)
GOAL: Set up the following post functions
-When Dev subtasks are moved to done, the story automatically transitions to the status of ready for test.
-When QA subtasks are moved from "In Test" to "Done", the story automatically transitions to post testing.
In short these are the auto transitions we would like to make
1st Dev subtask = In Progress, Story = In progress
All Dev subtasks = Done, Story = Ready fro Test
1st QA subtask = In progress and all Dev subtasks = Done, Story = In Test
All QA subtasks = Done and All Dev subtasks = Done, Story = Post Test
All Performance Test subtask = Done, Story = Done
I have found some info about how to do this here, but it has not been fully helpful in accomplishing my goal:
https://answers.atlassian.com/questions/268989