Hi all!
We are trying to create an automation with little success... These are the conditions.
We have Project A and Project B. When a issue is linked with another issue in the other project we need to:
1- Check issue dates.
2- If "Due Date" in Project B issue is furthest than "Due Date" in Project A, copy that "Due Date" in the Project A issue.
Thank you for your help!