New to Jira so still learning. But all tasks in each epic are sequential (and linked), and I want to be able to set the number of days for each task and the first tasks start/end dates and have the rest automatically populate. Similar to MS project - I want to be able to manipulate schedule with number of days - is this possible in Jira?
Started playing with automation - and got this far (see below) before I'm lost and don't know how to finish or even if I'm on track!
- When: Values change for
due date, start date
- If: linked issues present
types: all link types
- Then: Edit issue fields
start date
The number of days was helpful for working through tasks so would be useful if we can have it in Jira too - but not essential!
Any suggestions helpful please!!!