Dear Community
I am a Progect Manager for big team in Ukrainian airline. We have a project in Jira Work Management with multiple tasks and subtasks. A lot subtasts are linked to each othe (blocket by) as one task need to be finished before another one will start. And each subtask has some duration (number of days to be implemented) which is reflected in my project as start and due dates.
What I need:
When start date and/or due date is changed by the assignee for one linked subtask, start and due date authomatically need to be changed for other later linked subtask, but duration of that task need to be the same.
For example:
Start date Due date
Subtask 1 Oct 15 Oct 20
Subtask 2 Oct 21 Oct 28
Changed
Start date Due date
Subtask 1 Oct 17 Oct 23 manually changed
Subtask 2 Oct 23 Oct 31 automatically cganged by the rule
How to create such a rule?
Thank you
BRGDS
Olena