Hi all,
I want to automate the following:
- Subtasks for each status
- When all subtasks are done in their respective status, I want the task to move to the next status -- where it will subsequently be auto-populated with more subtasks
Building subtasks per status is easy enough, as well as subtasks done --> parent task transition. But when I automate the subtasks = done --> change parent task, the subtasks for the new status don't auto-populate... only when I manually transition the status.
Attempt 1:
- When --> transition --> to [particular status]
- Then --> create subtasks
Attempt 2:
- When --> value change in status
- If status equals [particular status]
- Then --> create subtasks
Obviously I'm thinking too simply, but I'm newer to Jira (a Notion gal at heart). Please help!