| Area | Definition |
| Defect density | Total Defects/ No Of Tests executed |
| Defect priority | Urgency of fixing a defect - Highest/High/Medium/Low/Lowest |
| Defect status | Curent state of the defect -Backlog/Inprogress/Building/Designing/Blocked/Ready to Test/E2E Testing/ Ready to Release/Done |
| Defect Aging (Open - Closed) | Period between the time the defect is detected and the time it was resolved [Status - Backlog to Done] |
| Defect triage - unknown to comp | Triaging and allocate defect to component for investigation/fix [ Component - Unknown to 'XXX'] |
| Defect RFT | allocating defect to the right component for the fix, Right First Time [ Initial component = Final Component] |
| Defect turnaround time (Open - Fixed) | Period between the time the defect is detected and Component fix delivered (multi fixes) [ Status - [Backlog]/Inprogress to E2E Testing] |
| Rejected Defect | Invalid Defects are rejected by SME's before asisgning to component [Internal] |
| Defect root cause | Reason for failure- Requirement/Design/Development/Deployment/Not a Defect |
| QOI Defects | Defects agreed as Valid. [except Root cause- Not a Defect] |
| Retest Timeline | Time taken to retest the defect (Status - E2E Testing to Done] |
| Defect retest failure | Defects fixed and Retest Failed. Assigned to the component for incremental fix. [Status - E2E Testing to Inprogress] |
| Quality of Requirement/Design | Defects Closed with Root cause as Requirement / Design |
| Quality of Test - QOO | Defects identified in Production / LVT for the stories signed off by E2E Test |
| Quality Of Dev -QOI | Defects identified against each component in E2E Testing |
| CST - Cov/pass rate | CST Coverage and Passrate of priority testcases for the specific Release Train |
| # of Requirements [Features / Stories] | Features / Stories scoped for a Release - Journey wise / Project wise / Release wise scope details |
| # of Tests [NF] - Test Status | Testing Status - Blocked/To Do/ Descoped/ Pass / Fail/ Executing |
| # of Tests [Regression]- Test Status | Testing Status - Blocked/To Do/ Descoped/ Pass / Fail/ Executing |
| # passed RFT [NF/REG] | Tests passed RFT. [Status - Todo to Passed] |
| 3 of MD's | Number of Maintanence Drop in a release |
| # of MD Scope | Test scope for each MD |
| # of MD Tests | Testing Status - Blocked/To Do/ Descoped/ Pass / Fail/ Executing |
| # of Requirement Signed off - Main and MD | No of Features/ Stories signed off from Release Scope |
| Requirement available for testing (Day1, 1+WK) | Code available for testing the story. [Day that any test scripts [under each Feature/Story] changed to Pass/Fail] |
| # of Requirement added post baseline- Test Scope | Requirements mapped to Release post Release baseline. [Manual Data] |
| Release Sign off Status (Cov/Pass rate) | Coverage and Pass rate on the Sign off Day |
| Environment availability | Testing blocked due to defects/issues in Test environment. Note: New Field to be created to get this metric |
| Execution per day | Total scenarios executed on each day (Status - Pass/Fail) |
| Test Position (Cov/Pass rate) | Coverage - (Pass+Dail+Executing)/ In Scope (Total Tests- Descoped) ; Pass rate - Pass/ In Scope (Total Tests- Descoped) |
| Defect Transition | Component transaction in the defect Lifecycle [Component - Orbit->Vlocity [1], Vlocity ->Orbit[2]) |
| Repeat Failure | Issue reocurring multiple times. (Need to check in Issue Summary ) |
| Defect detection rate | Week on Week Defects detection From Release Start |
| Defect Phase containment | Defects raised and closed within the Release timeline |