hi everyonei have epic ticket under the epic ticket there are many task tickets linkedso my question is is there any possible way if we enter duedate in epic ticket automatically update task tickets with deferent due dates ( for each task need saparate due dates while changing te due date in epic ticket)please someone help me
Hi @MURUGESH S - This is definitely possible, but it would help if you provide a little more context. Is your expectation that the due date will be dynamically determined based upon some type of business logic? If so, what is that business logic?
It’s not a one time thing or dependent on user input so i need automation for if we enter duedate in epic ticket automatically update task tickets with deferent due dates ( for each task need saparate due dates while changing te due date in epic ticket)
Requirement example i have one EPIC under that 4 task issues are linked EPIC due date =1-8-2023 if i enter this dude date in epic .the due dates of tasks wil be automatically updated like this task1=1-2-2023task2= 1-3-2023
task3= 1-1-2023task4=1-4-2023Is this possible ????
Yes it's possible, but need to make sure the business logic is repeatable. For example, will task 3 always be 7 days before, task 1 always be 6 days before, task 2, 5 days before, etc?
Automation needs repeatable parameters: