Hello,
I have multiple teams in my Portfolio 2.0 plan and they all use the same sprints, but when I try to view their capacity Portfolio makes me switch to Team View and then still doesn't show the capacity calculations. If I filter down to a single team, it does show me the accurate capacity for that team. The sprint setup is controlled on one central sprint board, but each team does have their own board referencing the master sprint board.
What do I need to do to have the capacity show up across all the teams? It is very inconvenient to switch to each team to see capacity.
Screen Shot 2016-09-28 at 4.32.35 PM.png
Screen Shot 2016-09-28 at 4.32.42 PM.png
Screen Shot 2016-09-28 at 4.33.05 PM.png