Hi,
Our PI consists of a combination of scrum and kanban teams. When we are reviewing our Program Board and addressing red items on the board, it was because the 'target completion' was outside of PI. Upon reading, this field is autocalculated.
Our Kanban teams want the ability to edit the target completion field and manually set vs system auto setting based on the teams JA 'throughput' settings.
How are your RTEs managing to this? Are you using the overwrite option for the team's 'throughput' setting? What ways do you work around this so the board doesn't unnecessarily flag something red?