I am trying to use the timeline view to manage the dependencies between my tasks, but it is missing some links, and showing other incorrectly.
For example, here's a link according to the timeline view:

And here's the detail of one of those tasks:

As you can see - the timeline view is showing the "relates to" link as a "blocks" link, and it isn't showing the 3 "blocked by" links.
As I understand it, the timeline should only show the blockers, and not the "relates to" (and it certainly shouldn't be misreporting a "relates to" as a "blocks".
I'm concerned that without being able to trust that the timeline is showing the dependencies accurately, I can't really use it as a tool to map out my workload!?
Any help would be appreciated...