We are wanting to track issues in a Sprint, the trouble is they don’t get closed in JIRA terms within the sprint. The workflow is as follows:-
- Scoping
- Approval
- Approved
- Assigned
- In Work
- QA
- UAT
- Closed
In Sprint terms the Scrum Board is mapped as follows:-
- Approved (Left Most Column, also defines backlog)
- Assigned
- In Work
- QA
- UAT (Right Most Column)
I’d like the Sprint, when closed, to recognise the items in the right most column (they essentially have the UAT status) as DONE. Is this possible?
The reason for this is the UAT is done by a different team to the development team, often involving third-parties and other complexities so the dev teams definition of done is matched against requirements, etc, so they can move forward onto other work (if UAT fails it will result in different tasks in future Sprints).
At the moment, the Sprint seems to be only recognising tasks as Done if they are actually closed. I can't be the only one who wants valid statuses on his issue pre and post those relevant for the Sprint?