Hello,
I checked for a few weeks on the community boards and see if someone is experiencing the same issue.
I have a task and a set of sub tasks with different due dates. For example :
- Task A (due date : March 8)
- Sub Task A (due date : March 1)
- Sub Task B (due date : March 8)
- Sub Task C (due date : March 15)
I try to set Task A due date for March 15 manually, but for some odd reason, everytime I place Task A into "In Progress" it forces it back into March 8 and I cannot seem to correct it.
If I change the due date of Sub Task B to any dates, the Task A will follow when I place it back into "In Progress". This would not happen to Sub Task C.
I use to have the same issue where a due date would always reset to the day the ticket was created, but it appears to have been fixed with the new update. I say appears as I am just not sure anymore and the due date is driving us crazy.
I turned off all Big Picture plug ins, I am not using any post functions, I am not using any scripts that could potentially do this. However, I am using Roadmaps Advanced.