I'm trying to write a query to tell me which stories were assigned points in the last sprint (2 weeks). A query for understanding if the points were changed within this time period would also be acceptable. This would be helpful because it would allow me to understand what scope is adding points to my overall backlog.
I often run into problems like "Your team has completed 50 points last sprint but the overall backlog grew by a net of 25 points. The delivery date is now late". I need to understand why this growth is happening. (Yes, it's happening because Product Owners are adding stories or pointing existing stories during refinement) but categorizing this added scope is my end goal.