Hi Team,
Is there a way to get a snapshot of what the backlog was for our JIRA project at a given point in time? We're hoping to write a query for this to get quarterly data points going back the last few years and trying to figure out if that's even possible/how we might go about doing this.
Hi Lakshmi
Try something like: project = ABC and status was "BACKLOG" on 2023-04-01
That should show you every issue on that project that was in the Backlog status on April 1, 2023. Change the dates and status as needed.
Hi @John Funk ,
It worked. Thank You.
Great! Glad it worked for you.