Dear community,
I try to calculate when a project feasibility should start.
I have the total jobsize e.g. 200
-> 10% of Jobsize= the amount of days necessary for the feasibility phase
--> I created a structure formula column named: FeasibilityJobSize (200*(10/100)) -> Numerical value
-> Additionally I know the deadline of the project e.g. 25/03/2023
Now I want to know when the Feasibility phase needs to finish in order to deliver on time.
Therefore I want to create an additional formula column:
FeasibilityDueDate
-> 25/03/2023 - FeasibilityJobSize (e.g. 20)
-> The result I want to obtain is 5/03/2023 (= 25/03/2023 - 20days)
What should my formula (Expr language) look like to obtain this result ?
Many thanks for your all feedback/support!