In the velocity chart report, when calculating the completed or committed estimates, which issue types are considered? Thank you in advance.
All parent tasks are considered. Estimates from sub-tasks are not included in the Velocity Chart's calculation.
All issues that are of a base type are sprint items. Sub-tasks and Epics and layers above Epic are not sprint items, so they are ignored. Sub-tasks are part of their parent, the estimate on the parent is assumed to include any sub-task.